You can now revert all your delayed tasks in a project.
1. Log into your account and select the project.
2. Locate the delayed task you need to revert. Click on the '...' icon on the left under 'Actions' column, and select 'Edit Task'.
3. In the task window, click the drop down for the 'Task Delayed'. This will provide two options; Yes or No. Select the appropriate setting and click Save at the bottom.