1. To add Tasks, Phases, or Milestones as children of other Tasks, Phases, and Milestones, start on the Task List screen.
  2. Click on the 3 dots next to the task you want the new item to be added under.
  3. Click on ‘+ Add New’ and the New Task screen is displayed. Note that new tasks can be added to existing tasks only as long as the existing tasks do not have resources assigned to them. Please see Resource Allocation for additional information.