• Starting on the Projects page, you want to click the name of the project you want to work on. When you select a traditional project, you will be directed to the Tasks tab. On this page, the import button is the 5th one on the tasks toolbar.
  • Clicking the Import button will open the pop-up import window. Copy list of tasks from an existing plan in excel, csv or mpp and paste them in the pop-up window under Task Name. Copy the duration in days from excel, csv or mpp and paste them under the Duration label in the pop up. When finished adding tasks, click the blue “Create Tasks” button to import the tasks and duration to the ListView.

Rows are automatically added once you paste data.